For most fleets, charging, not the truck, is the hardest part of going electric. This guide walks through the decisions that determine whether a battery-electric truck program succeeds: where to charge, how much power you need, how long it takes, and what it costs.
| Option | Best for | Trade-offs |
|---|---|---|
| Depot charging (your own site) | Return-to-base routes: drayage, regional delivery, refuse, and local pickup and delivery. | Lowest cost per mile and full control, but needs capital, utility upgrades, and land. |
| Public or shared truck stops | Trucks that cannot return to base each night, and top-up charging. | No construction, but heavy-duty sites are still scarce and pricing is higher. |
| Charging-as-a-service | Fleets that want to avoid upfront capital or lack suitable property. | A provider builds and runs the chargers for a per-kWh or monthly fee. Contract terms matter. |
Start from your duty cycle, not the charger catalog. For each truck, estimate daily miles, the energy use per mile from the manufacturer, and how many hours it sits at the depot. Overnight dwell of eight hours or more usually means lower-power chargers are enough. Short dwell times call for faster, more expensive charging.
Large depots may require substation upgrades, which can stretch timelines further. Phase your fleet rollout to match the power you can actually get.
Your electricity bill has two parts that matter: the energy charge (per kWh) and the demand charge (based on your highest power draw in a billing period). Demand charges can make fast, simultaneous charging very expensive. Ways to manage them include:
See our live heavy-duty station data for current counts of truck-capable charging, Megawatt Charging System sites, and hydrogen stations by state, updated automatically from the U.S. Department of Energy.
Find public charging and planned heavy-duty sites with the Department of Energy’s Alternative Fuels Station Locator.
See also: Charging Infrastructure · Charging Basics · Operating Zero-Emission Trucks